Community Centre Update – 13th December, 2024
Welcome to the latest community centre build progress report NR 02! As Hutton Construction continue to work diligently on constructing our modern and versatile community facility for Newhall residents, we are excited to share the most recent advancements in the project. The full downloadable report highlights the significant progress made across multiple areas, including site clearance, attenuation crate installation, car park development, foundation works and waterproofing. Hutton’s and Newhall Project Ltd are committed to providing regular updates, ensuring transparency throughout the build process. Thank you for your continued interest and support as we work together to create an exceptional space that will serve the diverse needs of our community for years to come.
Progress Report Nr 02 – Summary:
Hutton Construction are pleased to report significant advancements in various aspects of the project including:
- Site Clearance: The remaining trees along the east boundary have been felled, successfully completing the site clearance.
- Attenuation Crates: The below-ground attenuation crates have been installed, ensuring efficient stormwater management.
- Car Park Area: The reduced level dig and sub-base installation for the car park area are now complete, paving the way for further development.
- Foundation Works: Excavation and concrete works for foundations between G/L 9-13 have commenced and are partially completed.
- Heating Trenches and Waterproofing: The heating trenches and RIW waterproofing works have been successfully completed, ensuring efficient temperature management and safeguarding structures against water damage.
- Below Ground RC Upstand Walls: Construction efforts on the below-ground RC upstand walls between G/L 1-8 are ongoing.
These achievements reflect Hutton Construction’s continued commitment to efficient progress and maintaining the highest standards throughout the development of the project. Please TAP: PROGRESS REPORT Nr 02 to read more detailed information and to see progress photos!
Community Centre Update – 5th November, 2024
Design and Access Statement – Barbara Weiss Architects
We have now added the Design and Access Statement by the reknown Barbara Weiss Architects to the Community Centre Development page. Please TAP here to read more!
Community Centre Update – 12th September, 2024
Planning Information
Curious about the Newhall Community Centre plans? Get all the details you need by exploring relevant planning applications on the Harlow Council website. Simply follow this link and stay informed about the exciting developments in your community: https://bit.ly/SearchHarlowPlanningApplication. Please use the following reference numbers in the search bar:
- HW/CND/24/00365
- HW/PL/15/00094
- HW/CND/24/00197
- HW/REMVAR/24/00037
- HW/REMVAR/23/00353
Community Centre Update – 8th August, 2024
Planning Consent Given
Newhall Projects Ltd, working with Barbara Weiss Architects (BWA) has secured consent to create an oak-framed community hall reusing the structure of a historic barn in Newhall.
Harlow Council have approved proposals to restore and repurpose a rundown agricultural building on the eastern edge of Harlow.
The 325m² scheme will create a 120-capacity hall to be used by residents of the ever-growing Newhall estate, which started construction in the early 2000’s.
The community hall and facility is set to begin construction in September 2024. This project marks one of the final phases of the Newhall development and aims to provide a functional and inviting space for the local community.
London based architects, BWA, in collaboration with timber frame experts The Green Oak Carpentry Company and sustainability consultants Supernatural Studio, have designed an innovative low-carbon building that pays homage to the agricultural heritage of the area. The project combines traditional materials with cutting-edge sustainable technology.
Newhall Community Centre – View Across the Square
Newhall Community Centre – Proposed Elevation Drawings
Restoration
At the heart of the project is the restoration and re-use of a historic oak-framed barn located on the site. The new design incorporates this restored structure alongside a new oak frame, Hempblock walls, wood fibre insulation, and traditional red timber cladding. Large pitched zinc roofs complete the design, adding a modern touch to the rustic aesthetic.
This project demonstrates a successful balance of preserving local history and providing a contemporary, eco-friendly facility that will serve the community for years to come.
Capital Costs
The full capital cost of the build is being met by Newhall Projects Ltd at no cost to residents. This means that there are NO capital cost repayments to be made by residents for the build.
Business Plan
With regard to the business plan for the community hall, this has yet to be submitted to and agreed with Harlow Council and once this is done, and approved we can share this with the community. The S106 that requires this is still with Harlow Council for signing so presently Newhall Projects Ltd is not able to progress this matter formally.
We are not yet in a position to finalise the costs until the final specification has been agreed and contract awarded, as this will then need to be converted into a longer-term capital expenditure maintenance budget for the hall, which will inform the business plan, along with normal running costs and any income generated by the hire of the hall.
Once transferred to the Residents Association and open to the public, the hall will be available to local Newhall community and groups to hire at a discounted rate to the wider public under the S106 terms.
Images and Photographs: Courtesy of Barbara Weiss Architects.
Community Centre Update – 21st September, 2023
Community Centre Update – 25th August, 2023
What’s Happening to the Old Barn
Newhall Residents get ready for some exciting news! The old barn that you can see from The Chase, is going to be painstakingly restored and will become the Newhall Community Centre. The image shown is a concept drawing of what the Newhall Community Centre could look like.
Long Process
There are many steps to the process and week commencing 21st August, 2023 you will notice scaffolding being erected around the barn. This is so the restorers can dismantle the barn and begin to take detailed photographs capturing images of all parts of the barn, inside and out, to document its current state.
It will then be taken offsite, where the they will use traditional materials that match the original construction, including using reclaimed wood, period-appropriate hardware and materials. An interesting historical fact, is that some of the reclaimed wood has actually come from fallen Oak tree branches in Newhall over the years, prepared and stored by Basil one of the original and last remaining Farm Hand.
Basil, New Hall Farm
Reclaimed Oak
They will then return it to Newhall, where it will be reassembled and become our new community centre.
Early Stages
Please remember the development is in its early stages, but we wanted to let the community know what’s happening, as there is likely to be quite a bit of activity on and around the site in the forthcoming months.
Keep an eye out here, or on our Facebook and Instagram accounts for news and updates!
- First published: 25th August, 2023
- Revised: 21st September, 2023
- Revised: 8th August, 2024
- Revised: 9th August, 2024
- Revised: 12th September, 2024
- Revised: 15th October, 2024
- Revised: 5th November, 2024
- Revised: 13th December, 2024
Leave A Comment